yesterday
September 2023 work started at CF64 4NR [outside a Tesco] at the end of my street to plant a phase 9 mast.
April 2024 it was complete with fibre & power connected & hardware in the cabinets. However it's the end of 2024 & it's still not powered on.
[There has been some 5G tests from the main site for my village that was only for a few days this year & going out at very low power.]
Any thoughts when this new mast might be powered up as it's been ready from a visual point of view for around 8 months.
Thank you